Final pricing error identified by vSPD
On the morning of 11 December 2012 our vectorised scheduling pricing and dispatch (vSPD) model indicated final prices at Dargaville (DAR0111) were slightly higher than prices published by the pricing manager for two trading periods on 10 December 2012.
Stage: I (Enquiry) | Status: Complete | Date commenced: 11/12/2012 |
Further investigation revealed that the incorrect values for load at DAR0111 had been used by the pricing manager, causing the pricing manager to publish prices that were $0.62/MWh and $0.68/MWh lower than they should have been for trading periods 16 and 17 on 10 December 2012 respectively.
-
Final pricing error identified by vSPD