Dispatch of unscheduled generation: 23-27 January 2011
Stage: II (Review) | Status: Complete | Date commenced: 01/02/2011 |
We released a report on events surrounding plant being constrained on in late January 2011, particularly Huntly Unit 5 on 23-27 January 2011.
-
Dispatch of unscheduled generation report - January 2011
dispatch-unscheduled-generation-Jan11.pdf (PDF, 848 KB)
Last updated: 28 June 2015
On 11 February 2011, we received a letter from the System Operator answering six questions asked on 1 February 2011.
-
11 February 2011 letter from System Operator to Electricity Authority
SO-ltr-11Feb11.pdf (PDF, 379 KB)
Last updated: 28 June 2015
On 22 February 2011, we received a letter from Contact Energy expressing concern at the magnitude of constrained-on payments for January 2011.
-
22 February 2011 letter from Contact Energy to Electricity Authority
Contact-ltr-22Feb11.pdf (PDF, 131 KB)
Last updated: 28 June 2015
On 23 February 2011, we went back to the System Operator with an additional four questions. The System Operator sent us a letter answering those questions on 28 February 2011.
-
28 February 2011 letter from System Operator to Electricity Authority
SO-ltr-28Feb11.pdf (PDF, 134 KB)
Last updated: 28 June 2015
On 2 March 2011, we received a letter from Genesis Power answering four questions asked on 28 January 2011.
-
2 March 2011 letter from Genesis Power to Electricity Authority
Genesis-ltr-2Mar11.pdf (PDF, 55 KB)
Last updated: 28 June 2015
On 18 March 2011, we received a letter from Mighty River Power expressing concern at the magnitude of constrained-on payments for January 2011.
-
18 March 2011 letter from Mighty River Power to Electricity Authority
MRP-ltr-18Mar11.pdf (PDF, 131 KB)
Last updated: 28 June 2015
The System Operator sends a daily report to the Market Administrator each day just after 7:00am. The daily report covers the previous 24-hour period and provides a comprehensive list of potential breaches of the code, adjustments to the pre-dispatch schedule, discretionary action, and block and station security constraint notices issued by the System Operator. The 26 January 2011 daily report is presented below as an example.
-
System Operator daily report to the Market Administrator - 26 January 2011
SO-daily-report-26Jan11.pdf (PDF, 81 KB)
Last updated: 28 June 2015