Avoided Cost of Transmission payments
The Authority is proposing to amend the Code to make it clear that payments by distributors to eligible distributed generation for avoided cost of transmission (ACOT) are no longer required
Overview
Date | Activity |
---|---|
20 Dec 2022 | Development: Decision on Code change for Avoided Cost of Transmission payments Read more |
16 Sep – 25 Nov 2022 | Consultation: The Authority asked Transpower further questions on specific aspects of the ACOT consultation paper and selected submissions regarding grid reliability. The Authority is now seeking feedback on Transpower’s response. Read more |