Proposed amendment to the HHR switching process for AMI switch event meter readings
Closed
20 Jan – 24 Feb 2015
12 submissions received (view submissions)
The Authority is consulting on a draft Code amendment for the use of AMI meter readings in the ICP switching process. The proposed amendment would benefit consumers during the switching process by ensuring that, when there is an AMI meter, retailers use accurate switch event meter readings for consumer invoicing
Consultation Papers
-
Consultation paper - Proposed amendment to the HHR switching process for AMI switch event meter readings
Last updated: 24 June 2015
Summary of submissions
-
Decisions paper
Amendment-to-HHR-switching-decisions-paper.pdf (PDF, 615 KB)
Last updated: 04 August 2015
-
Summary of submissions
Last updated: 16 July 2015
Submissions
-
Download a ZIP file containing all documents
-
Contact Energy
Contact-Energy.pdf (PDF, 79 KB)
Last updated: 24 June 2015
-
Ecotricity
Last updated: 24 June 2015
-
Electric Kiwi
Electric-Kiwi.pdf (PDF, 408 KB)
Last updated: 24 June 2015
-
emhTrade
Last updated: 24 June 2015
-
Flick Energy
Flick-Energy.pdf (PDF, 120 KB)
Last updated: 24 June 2015
-
Genesis Energy
Genesis-Energy.pdf (PDF, 134 KB)
Last updated: 24 June 2015
-
Giving Energy
Giving-Energy.pdf (PDF, 77 KB)
Last updated: 24 June 2015
-
Meridian Energy
Meridian-Energy.PDF (PDF, 148 KB)
Last updated: 24 June 2015
-
Mighty River Power
Mighty-River-Power.pdf (PDF, 60 KB)
Last updated: 24 June 2015
-
Nova Energy
Last updated: 24 June 2015
-
-
Switch process re-engineering - Review of Schedule 11.3
Closed
20 Dec 2013 – 28 Feb 2014
15 submissions received (view submissions)
The Authority invites submissions on the regulatory statement and the proposed amendment, including drafting comments for an amendment to Schedule 11.3 of the Code. The purpose of these proposed amendments is to improve the efficiency of the process for switching ICPs between traders.
When the new Part 10 and associated amendments to Parts 1, 11 and 15 (new metering rules) were being implemented (Part 10 implementation project), it was identified that half-hour (HHR) certified and reconciled advanced metering infrastructure (AMI) metering installations created issues for the process used to switch ICPs between traders.
To overcome these issues, and so enable the new metering rules to function as required, a new switch completion file (known as the CS file), and Code amendments for ICP switching were included in the Part 10 implementation project. The intention was that the switching process would be fully reviewed after the new metering rules came into effect and participants had some experience with switching HHR AMI metering installations, to ensure that this issue and other issues raised by participants were addressed.
Experience since the new metering rules came into effect on 29 August 2013 suggests that the changes made in the Part 10 implementation project appear to be working effectively, and only minor changes to the ICP trader switching process appear to be required. This paper proposes a number of amendments to the processes set out in Schedule 11.3 that are expected to facilitate the efficient switching of HHR metering installations.
Consultation Papers
-
Consultation Paper - Switch process re-engineering Review of Schedule 11.3
Consultation-paper-switch-process-review-13.5.pdf (PDF, 280 KB)
Last updated: 18 August 2016
Summary of submissions
-
Decisions and reasons paper
Decisions-and-reasons-switch-process-re-engineering.pdf (PDF, 513 KB)
Last updated: 24 June 2015
-
Summary of submissions
HHR-summary-of-submissions.pdf (PDF, 343 KB)
Last updated: 24 June 2015
Submissions
-
Download a ZIP file containing all documents
-
2 Confidential submissions have not been published
2-Confidential-submissions-have-not-been-published.pdf (PDF, 28 KB)
Last updated: 17 August 2016
-
Contact
Last updated: 17 August 2016
-
Craftware Computing Limited
Craftware-Computing-Limited.pdf (PDF, 18 KB)
Last updated: 17 August 2016
-
Energy Direct NZ
Energy-Direct-NZ.pdf (PDF, 135 KB)
Last updated: 17 August 2016
-
Flick Energy Limited
Flick-Energy-Limited.pdf (PDF, 191 KB)
Last updated: 17 August 2016
-
Genesis Energy
Genesis-Energy.pdf (PDF, 110 KB)
Last updated: 17 August 2016
-
Meridian Energy Limited
Meridian-Energy-Limited.pdf (PDF, 182 KB)
Last updated: 17 August 2016
-
Metrix
Last updated: 17 August 2016
-
Mighty River Power Limited
Mighty-River-Power-Limited.pdf (PDF, 145 KB)
Last updated: 17 August 2016
-
Nova Energy
Last updated: 17 August 2016
-
Contact Us
EMAIL: info@ea.govt.nz
Sign up to our newsletter
© 2023 Copyright material on this site is protected by copyright owned by the Electricity Authority or its licensors. Full copyright statement.