Monitoring compliance of routine testing of assets - as at 30 June 2017
The Authority’s compliance team is asking asset owners to confirm that they have tested their assets in accordance with the technical requirements set out in Part 8 of the Electricity Industry Participation Code 2010 (Code).
Clause 8(2)(a) of Technical Code A of Schedule 8.3 of the Code requires each asset owner to carry out periodic testing of its assets in accordance with Appendix B of Technical Code A of Schedule 8.3.
Asset owners are requested to complete the relevant workbook below with information, including the details of the asset and the date of the testing, as at 30 June 2017. Each workbook contains an instruction sheet.
Workbooks to confirm routine testing:
Please send your completed workbook to compliance@ea.govt.nz by Monday 21 August 2017.