Settlement Agreement approved
|
|
The Authority has issued a strong warning letter to Transpower as the grid owner and approved a settlement agreement between Transpower New Zealand Limited and Contact Energy Limited following a self-reported breach by the grid owner.
The grid owner breached the Code on 25 October 2019 when it used incorrect terminal numbers on drawings. This resulted in incorrect wiring that resulted in a replacement circuit breaker initiating a trip of all generation at Contact Energy’s Ohaaki power station.
The settlement is available to view on our website.
|
|
The Authority welcomes submissions on our current consultations
|
|
The Authority is consulting on the 2021 Dry Year event review, the 9 August UTS claim preliminary decision, and the proposed settlement residual allocation methodology (SRAM). Consultation on the Dry Year event review closes at 5pm today. Consultation on the UTS claim preliminary decision closes at 5pm on 3 February 2022, and consultation on the proposed SRAM principles closes at 5pm on 1 March 2022
See our list of current consultations below to make a submission.
|
|
|
|
|
|
2021 Dry Year event review
Ending: 5pm today, 25 January 2022
|
|
|
9 August 2021 - UTS Preliminary Decision
Ending 5pm, 3 February 2022
|
|
|
Proposed SRAM Principles
Ending 5pm, 1 March 2022
|
|
|
Level 7, Harbour Tower, 2 Hunter Street, PO Box 10041, Wellington 6143, New Zealand
Tel: + 64 4 460 8860 Email: communications@ea.govt.nz
|
|
|
|
|